Construction work between Busto Arsizio and Malpensa Airport

Scheduled

Affected Lines

  • Malpensa-Milano Cadorna
  • Malpensa-Milano Centrale
  • Malpensa-Saronno-Milano Centrale
  • Biasca-Bellinzona-Lugano-Varese-Malpensa

Period(s) of Work

September 21 - September 22 2025

from 10:00 PM to 6:00 AM

September 25 - September 26 2025

from 10:00 PM to 6:00 AM

September 29 - December 05 2025

from Tuesday/Wednesday to Friday/Saturday, excluding the nights from 28/29 October to 31 October/01 November.

September 28 - December 01 2025

Monday/Tuesday nights from 6:00 PM to 6:00 AM, except October 27/28

September 29 - December 12 2025

Only for XP1 trains Milan Cadorna – Malpensa A. T2

Intervention: Scheduled maintenance work between the Busto Arsizio Nord and Malpensa Aeroporto T2 stations and Busto Arsizio FS and Malpensa A. T2 stations.

Travel options:

  • Changes to trains operating during the affected time slots.
  • Replacement bus service for nighttime disruptions.